Gateway
NVTA-Funded Projects
Projects
FUNDEDNVTA Funding
ALLOCATEDProject Funding Sources
Project Status
Shows the activity status of all NVTA-funded projects
Transportation Mode
NVTA funding makes a multi-modal future in Northern Virginia possible
NVTA Funding Status
Amount of NVTA funds allocated and spent
Title | Sponsor/Jurisdiction | Total Cost | Location(s) | Segment | Approved NVTA Amount | Primary Mode | Current Status | Anticipated Completion Date | |
---|---|---|---|---|---|---|---|---|---|
Details | Silver/Blue Line Mitigation (4 New Buses) | Arlington County | $1,000,000 | Arlington County | 1 | $1,000,000 | Bus | Project Complete | December 31, 2014 |
Details | Boundary Channel Drive Interchange | Arlington County | $22,533,000 | Arlington County | 1 | $4,335,000 | Intersection/Interchange | Project Underway | May 31, 2024 |
Details | Crystal City Multimodal Center | Arlington County | $1,712,500 | Arlington County | 1 | $1,500,000 | Bus | Project Complete | December 31, 2018 |
Details | Ballston Metrorail Station West Entrance | Arlington County | $150,000,000 | Arlington County | 1 | $92,000,000 | Rail | Project Underway | June 30, 2027 |
Details | Lee Highway Corridor ITS Enhancements | Arlington County | $3,000,000 | Arlington County | 1 | $3,000,000 | Transportation Technology (e.g. ITS) | Project Underway | June 30, 2025 |
Details | Crystal City Streets: 12th Street transitway | Arlington County | $20,510,000 | Arlington County | 1 | $11,600,000 | Roadway | Project Underway | December 31, 2025 |
Details | Glebe Road Corridor ITS Improvements | Arlington County | $2,000,000 | Arlington County | 2 | $2,000,000 | Transportation Technology (e.g. ITS) | Project Underway | June 30, 2024 |
Details | Columbia Pike Multimodal Street Improvements | Arlington County | $133,000,000 | Arlington County | 1 | $12,000,000 | Roadway | Project Complete | November 2, 2022 |
Details | Columbia Pike Multimodal Street Improvements - East | Arlington County | $110,000,000 | Arlington County | 1 | $10,000,000 | Roadway | Project Underway | June 30, 2025 |
Details | ART Operations and Maintenance Facilities | Arlington County | $63,812,000 | Arlington County | 1 | $39,027,000 | Bus | Project Underway | June 30, 2025 |
Details | Crystal City Metrorail Station East Entrance and Intermodal Connections | Arlington County | $89,061,000 | Arlington County | 1 | $5,000,000 | Rail | Project Underway | June 30, 2025 |
Details | Pentagon City Multimodal Connections and Transitway Extension | Arlington County | $43,985,000 | Arlington County | 2 | $28,850,000 | Bus | Project Underway | April 30, 2025 |
Details | Intelligent Transportation System Improvements | Arlington County | $10,000,000 | Arlington County | 2 | $10,000,000 | Transportation Technology (e.g. ITS) | Project Underway | June 30, 2025 |
Details | Duke Street Transit Signal Priority Installation | City of Alexandria | $850,000 | City of Alexandria | 1 | $850,000 | Transportation Technology (e.g. ITS) | Project Complete | September 30, 2019 |
Details | DASH Bus Expansion (5 New) | City of Alexandria | $3,250,000 | City of Alexandria | 2 | $1,462,500 | Bus | Project Complete | March 31, 2016 |
Details | West End Transitway: Northern Segment (Phase 1) | City of Alexandria | $73,901,000 | City of Alexandria | 2 | $4,600,000 | Bus | Project Underway | June 30, 2026 |
Details | Shelters and Real Time Information for DASH/WMATA | City of Alexandria | $1,967,750 | City of Alexandria | 3 | $450,000 | Bus | Project Complete | December 31, 2018 |
Details | Potomac Yard Metrorail Station Development | City of Alexandria | $384,725,000 | City of Alexandria | 1 | $69,500,000 | Rail | Project Underway | November 30, 2023 |
Details | Alexandria ITS Projects | City of Alexandria | $1,195,491 | City of Alexandria | 3 | $1,195,491 | Transportation Technology (e.g. ITS) | Project Complete | November 30, 2020 |
Details | Alexandria Bus Network ITS | City of Alexandria | $150,000 | City of Alexandria | 3 | $150,000 | Transportation Technology (e.g. ITS) | Project Complete | September 30, 2020 |
Details | DASH Transit Service Enhancements and Expansion (including 8 electric buses) | City of Alexandria | $23,068,161 | City of Alexandria | 2 | $11,933,161 | Bus | Project Underway | December 31, 2026 |
Details | Alexandria Duke St Transitway | City of Alexandria | $87,555,000 | City of Alexandria | 2 | $87,000,000 | Bus | Project Underway | June 30, 2028 |
Details | Cue 35-Foot Buses (6 New) | City of Fairfax | $3,000,000 | City of Fairfax | 2 | $3,000,000 | Bus | Project Complete | September 30, 2015 |
Details | Kamp Washington Intersection Improvements | City of Fairfax | $11,587,950 | City of Fairfax | 2 | $1,000,000 | Intersection/Interchange | Project Complete | December 31, 2017 |
Details | Northfax - Intersection Improvements at Route 29/50 and Route 123 | City of Fairfax | $42,676,113 | City of Fairfax | 2 | $15,000,000 | Intersection/Interchange | Project Complete | June 30, 2019 |
Details | Jermantown / Route 50 Roadway Improvements | City of Fairfax | $6,925,139 | City of Fairfax | 2 | $1,000,000 | Intersection/Interchange | Project Complete | June 30, 2016 |
Details | Jermantown Road Corridor Improvements Project | City of Fairfax | $21,000,000 | City of Fairfax | 2 | $21,000,000 | Roadway | Project Underway | September 30, 2026 |
Details | Intersection Improvements at Eaton Place/Chain Bridge Road | City of Fairfax | $10,850,000 | City of Fairfax | 2 | $10,750,000 | Intersection/Interchange | Not Yet Started | December 30, 2026 |
Details | Old Lee Highway Multimodal Improvements Phase 1 | City of Fairfax | $25,000,000 | City of Fairfax | 1 | $13,000,000 | Bike and Pedestrian | Project Underway | September 30, 2025 |
Details | Roadway Network Northfax West | City of Fairfax | $9,600,000 | City of Fairfax | 2 | $4,700,000 | Roadway | Project Underway | September 30, 2024 |
Details | Funding for Bus Shelters | City of Falls Church | $720,000 | City of Falls Church | 1 | $200,000 | Bus | Project Complete | June 30, 2017 |
Details | Pedestrian Access to Transit | City of Falls Church | $5,998,751 | City of Falls Church | 2 | $700,000 | Pedestrian only | Project Complete | June 30, 2018 |
Details | Pedestrian Bridge at Van Buren Street | City of Falls Church | $300,000 | City of Falls Church | 2 | $300,000 | Pedestrian only | Project Complete | March 31, 2017 |
Details | West Falls Church and Joint Campus Revitalization District Multimodal Transportation Project | City of Falls Church | $15,757,600 | City of Falls Church | 2 | $15,700,000 | Intersection/Interchange | Project Underway | August 31, 2024 |
Details | Route 28 Widening: Godwin Drive to the Southern City Limits | City of Manassas | $20,711,401 | City of Manassas | 3 | $3,294,000 | Roadway | Project Complete | June 6, 2023 |
Details | Innovation Center Metrorail Station | Fairfax County | $89,000,000 | Fairfax County | 2 | $69,000,000 | Rail | Project Complete | December 31, 2020 |
Details | Connector Buses (12 New) | Fairfax County | $6,000,000 | Fairfax County | 1 | $6,000,000 | Bus | Project Complete | March 31, 2016 |
Details | West Ox Bus Garage Expansion | Fairfax County | $20,000,000 | Fairfax County | 2 | $20,000,000 | Bus | Project Complete | December 31, 2019 |
Details | Fairfax County Parkway Widening from Ox Rd to Lee Hwy | Fairfax County | $108,160,624 | Fairfax County | 2 | $124,400,000 | Roadway | Project Underway | December 31, 2027 |
Details | Frontier Drive Extension & Interchange Improvements | Fairfax County | $138,000,000 | Fairfax County | 1 | $27,000,000 | Roadway | Project Underway | June 30, 2027 |
Details | Route 28 Widening: Prince William County Line to Route 29 | Fairfax County | $72,853,556 | Fairfax County | 3 | $26,000,000 | Roadway | Project Underway | May 24, 2024 |
Details | Rolling Road Widening - Old Keene Mill Road to Franconia Springfield Parkway | Fairfax County | $78,965,765 | Fairfax County | 1 | $43,811,000 | Roadway | Project Underway | December 31, 2026 |
Details | Route 1 Widening - Mount Vernon Memorial Highway to Napper Road | Fairfax County | $415,000,000 | Fairfax County | 1 | $308,595,000 | Roadway | Project Underway | December 31, 2028 |
Details | Route 7 Widening - Colvin Forest Drive to Jarrett Valley Drive | Fairfax County | $348,872,000 | Fairfax County | 2 | $10,000,000 | Roadway | Project Underway | July 31, 2024 |
Details | Route 28 Widening 6 to 8 lanes (NB from McLearen Road to Dulles Toll Road) | Fairfax County | $13,300,000 | Fairfax County | 1 | $11,100,000 | Roadway | Project Complete | September 30, 2016 |
Details | Route 28 Widening 6 to 8 lanes (SB from Dulles Toll Road to Route 50) | Fairfax County | $22,200,000 | Fairfax County | 1 | $20,000,000 | Roadway | Project Complete | December 31, 2016 |
Details | Route 7 Bridge Widening: Over Dulles Toll Road | Fairfax County | $44,822,467 | Fairfax County | 1 | $13,900,000 | Roadway | Project Complete | June 30, 2017 |
Details | Rock Hill Road Bridge | Fairfax County | $100,000,000 | Fairfax County | 1 | $20,604,670 | Roadway | Not Yet Started | December 31, 2027 |
Details | Richmond Highway Bus Rapid Transit - Phases I & II | Fairfax County | $730,000,000 | Fairfax County | 1 | $330,000,000 | Bus | Project Underway | December 30, 2031 |
Details | Richmond Highway (Route 1)/CSX Underpass Widening | Fairfax County | $56,000,000 | Fairfax County | 1 | $12,000,000 | Roadway | Not Yet Started | December 31, 2023 |
Details | Leesburg Park and Ride | Loudoun County | $4,760,660 | Loudoun County | 1 | $1,000,000 | Park and Ride | Project Complete | March 31, 2019 |
Details | Transit Buses (2 New) | Loudoun County | $880,000 | Loudoun County | 3 | $880,000 | Bus | Project Complete | December 31, 2013 |
Details | Transit Buses (4 New) | Loudoun County | $1,860,000 | Loudoun County | 3 | $1,860,000 | Bus | Project Complete | March 31, 2017 |
Details | Loudoun County Parkway Development | Loudoun County | $31,000,000 | Loudoun County | 1 | $31,000,000 | Roadway | Project Complete | October 30, 2023 |
Details | Belmont Ridge Road, North of the Dulles Greenway | Loudoun County | $56,805,386 | Loudoun County | 2 | $20,000,000 | Roadway | Project Complete | September 30, 2016 |
Details | Belmont Ridge Road Widening (Truro Parish Dr to Croson Ln) | Loudoun County | $42,736,000 | Loudoun County | 2 | $19,500,000 | Roadway | Project Underway | December 31, 2024 |
Details | Route 28 Northbound Widening – between Dulles Toll Road and Sterling Boulevard | Loudoun County | $20,000,000 | Loudoun County | 2 | $20,000,000 | Roadway | Project Complete | June 15, 2020 |
Details | Route 15 Bypass Widening: Battlefield Parkway to Montresor Road | Loudoun County | $81,163,683 | Loudoun County | 1 | $54,000,000 | Roadway | Project Underway | June 30, 2029 |
Details | Extend Shellhorn Road: Loudoun County Parkway (Route 607) to Randolph Drive (Route 1072) | Loudoun County | $180,106,309 | Loudoun County | 2 | $16,000,000 | Roadway | Project Underway | December 31, 2027 |
Details | Northstar Boulevard - Evergreen Mills Road (formerly, Shreveport Drive) to Tall Cedars Parkway | Loudoun County | $132,289,000 | Loudoun County | 1 | $64,805,000 | Roadway | Project Underway | December 31, 2024 |
Details | Prentice Drive Extension: Lockridge Road (Route 789) to Shellhorn Road (Route 643) | Loudoun County | $95,087,144 | Loudoun County | 2 | $76,230,000 | Roadway | Project Underway | February 14, 2027 |
Details | Dulles West Boulevard Widening: Loudoun County Parkway to Northstar Boulevard | Loudoun County | $59,314,000 | Loudoun County | 2 | $47,800,000 | Roadway | Project Underway | December 31, 2026 |
Details | Route 9 Traffic Calming | Loudoun County | $19,866,000 | Loudoun County | 1 | $12,112,000 | Intersection/Interchange | Project Complete | April 30, 2021 |
Details | Evergreen Mills Road Intersection Realignments – Watson Road and Reservoir Road | Loudoun County | $14,000,000 | Loudoun County | 3 | $14,000,000 | Intersection/Interchange | Project Underway | December 31, 2025 |
Details | Transit Alternatives Analysis Study in the Route 7 Corridor | NVTC | $838,000 | Arlington County, City of Alexandria, City of Falls Church, Fairfax County | 1 | $838,000 | Bus | Project Complete | June 30, 2017 |
Details | Route 28 Widening: Route 234 Bypass to Linton Hall Road | Prince William County | $70,900,000 | Prince William County | 3 | $69,700,000 | Roadway | Project Complete | December 30, 2022 |
Details | Route 1 Widening: Featherstone Road to Marys Way | Prince William County | $111,200,000 | Prince William County | 2 | $63,400,000 | Roadway | Project Underway | October 26, 2023 |
Details | Route 28 Corridor Roadway Improvements - East of Route 234 | Prince William County | $292,400,000 | Prince William County | 3 | $95,000,000 | Roadway | Project Underway | October 31, 2028 |
Details | Construct Interchange at Prince William Parkway and Clover Hill Road | Prince William County | $12,900,000 | Prince William County | 1 | $1,900,000 | Intersection/Interchange | Project Underway | May 31, 2026 |
Details | Construct Interchange at Prince William Parkway and University Boulevard | Prince William County | $24,200,000 | Prince William County | 2 | $24,200,000 | Intersection/Interchange | Project Underway | May 30, 2024 |
Details | Construct Interchange at Route 234 and Brentsville Road | Prince William County | $54,900,000 | Prince William County | 1 | $54,900,000 | Intersection/Interchange | Project Underway | August 31, 2024 |
Details | Summit School Rd Extension and Telegraph Rd Widening | Prince William County | $35,000,000 | Prince William County | 2 | $35,000,000 | Roadway | Project Underway | May 31, 2024 |
Details | PRTC New Gainesville Service (1 New Bus) | PRTC | $580,000 | Prince William County | 3 | $580,000 | Bus | Project Complete | September 30, 2014 |
Details | Western Bus Maintenance & Storage Facility | PRTC | $47,680,000 | Prince William County | 1 | $16,500,000 | Bus | Project Complete | September 30, 2020 |
Details | Route 1 (Fraley Blvd) Widening: Brady's Hill Road to Dumfries Road | Prince William County | $129,760,000 | Town of Dumfries | 1 | $129,760,000 | Roadway | Project Underway | February 28, 2026 |
Details | Herndon Metrorail Intermodal Access improvements | Town of Herndon | $5,862,061 | Town of Herndon | 1 | $1,100,000 | Bike and Pedestrian | Project Complete | July 31, 2023 |
Details | Herndon Parkway Intersection Improvements at Van Buren St | Town of Herndon | $3,110,000 | Town of Herndon | 1 | $500,000 | Intersection/Interchange | Project Complete | September 7, 2023 |
Details | Herndon Parkway Intersection Improvements at Sterling Rd | Town of Herndon | $500,000 | Town of Herndon | 1 | $500,000 | Intersection/Interchange | Project Complete | March 31, 2019 |
Details | East Elden Street Improvements & Widening | Town of Herndon | $45,522,566 | Town of Herndon | 2 | $10,400,000 | Roadway | Project Underway | September 30, 2026 |
Details | Interchange Improvements at Route 15 Leesburg Bypass and Edwards Ferry Road | Town of Leesburg | $185,074,950 | Town of Leesburg | 2 | $7,400,000 | Intersection/Interchange | Project Underway | December 31, 2030 |
Details | Route 7 (East Market Street)/Battlefield Parkway Interchange | Town of Leesburg | $68,258,541 | Town of Leesburg | 2 | $58,000,000 | Intersection/Interchange | Project Complete | November 18, 2021 |
Details | Construct Interchange at Route 15 Bypass and Battlefield Parkway | Town of Leesburg | $60,000,000 | Town of Leesburg | 1 | $2,000,000 | Intersection/Interchange | Project Underway | December 31, 2030 |
Details | Mill St NE Parking Garage | Town of Vienna | $4,600,000 | Town of Vienna | 1 | $2,300,000 | Park and Ride | Project Underway | February 28, 2026 |
Details | VRE Lorton Station Second Platform | VRE | $16,150,000 | Fairfax County | 1 | $800,270 | Rail | Project Complete | December 31, 2030 |
Details | Franconia-Springfield Platform Improvements | VRE | $13,000,000 | Fairfax County | 1 | $13,000,000 | Rail | Project Underway | December 30, 2025 |
Details | Rippon Station Expansion and Second Platform | VRE | $16,634,793 | Prince William County | 1 | $39,482 | Rail | Project Complete | December 31, 2030 |
Details | Slaters Lane Rail Crossover | VRE | $7,000,000 | City of Alexandria | 1 | $7,000,000 | Rail | Project Complete | September 18, 2020 |
Details | VRE Crystal City Station Improvements | VRE | $49,940,000 | Arlington County | 1 | $20,200,000 | Rail | Project Underway | June 30, 2028 |
Details | Manassas Park Station Parking Expansion | VRE | $30,433,503 | City of Manassas Park | 2 | $2,500,000 | Park and Ride | Project Underway | March 31, 2026 |
Details | VRE Gainesville-Haymarket Extension/Broad Run Expansion Project Development | VRE | $5,145,943 | Prince William County | 3 | $1,500,000 | Rail | Project Complete | February 28, 2027 |
Details | Blue Line Traction Power Upgrades | WMATA | $62,144,466 | Arlington County, City of Alexandria, Fairfax County | 2 | $17,443,951 | Rail | Project Underway | December 31, 2023 |
Details | Traction Power Upgrades on the Orange Line in Virginia | WMATA | $17,736,012 | Arlington County, City of Fairfax, City of Falls Church, Fairfax County | 2 | $4,978,685 | Rail | Project Complete | July 30, 2020 |
Details | Falls Church Enhanced Regional Bike Routes (W&OD) | City of Falls Church | $3,793,209 | City of Falls Church | 2 | $3,244,959 | Bike and Pedestrian | Project Complete | December 31, 2021 |
Details | Construct Crosstrail Boulevard (Route 653): Sycolin Road to Dulles Greenway (Route 267) | Loudoun County | $42,940,000 | Loudoun County | 1 | $36,700,000 | Roadway | Project Underway | June 30, 2027 |
Details | Evergreen Mills Road Widening from Northstar Boulevard to Stone Springs Boulevard | Loudoun County | $35,500,000 | Loudoun County | 1 | $18,000,000 | Roadway | Not Yet Started | June 30, 2027 |
Details | Arlington W&OD Trail Enhancements | Arlington County | $5,646,000 | Arlington County | 1 | $650,000 | Bike and Pedestrian | Not Yet Started | June 30, 2025 |
Details | Government Center Parkway Extension | City of Fairfax | $7,500,181 | City of Fairfax | 1 | $3,540,000 | Roadway | Project Underway | June 30, 2025 |
Details | Jermantown Road/Route 29 Intersection Improvements | City of Fairfax | $1,400,000 | City of Fairfax | 1 | $700,000 | Intersection/Interchange | Not Yet Started | June 30, 2026 |
Details | University Boulevard Extension: Devlin Road to Wellington Road | Prince William County | $100,000,000 | Prince William County | 2 | $53,000,000 | Roadway | Not Yet Started | June 30, 2027 |
Details | North Woodbridge Mobility Improvements: Annapolis Way Connector | Prince William County | $8,300,000 | Prince William County | 1 | $8,000,000 | Roadway | Project Underway | August 29, 2024 |
Details | Van Buren Road North Extension: Route 234 to Cardinal Drive | Prince William County | $82,000,000 | Prince William County | 2 | $8,000,000 | Roadway | Project Underway | June 30, 2030 |
Details | Soapstone Drive Extension from Sunset Hills Road to Sunrise Valley Drive | Fairfax County | $235,000,000 | Fairfax County | 1 | $88,793,037 | Roadway | Not Yet Started | June 30, 2030 |
Details | Seven Corners Ring Road Improvements | Fairfax County | $94,800,000 | Fairfax County | 2 | $4,200,000 | Intersection/Interchange | Not Yet Started | June 30, 2030 |
Details | Downtown Falls Church Multimodal Improvements | City of Falls Church | $10,540,000 | City of Falls Church | 2 | $8,300,000 | Bike and Pedestrian | Project Underway | June 30, 2026 |
Details | CC2DCA Intermodal Connector | Arlington County | $36,177,000 | Arlington County | 1 | $18,000,000 | Bike and Pedestrian | Project Underway | June 30, 2026 |
Details | Rosslyn Multimodal Network Improvements | Arlington County | $11,874,000 | Arlington County | 1 | $11,874,000 | Bike and Pedestrian | Not Yet Started | June 30, 2026 |
Details | West Falls Church Access to Transit and Multimodal Connectivity | City of Falls Church | $6,900,000 | City of Falls Church | 2 | $6,900,000 | Bike and Pedestrian | Project Underway | March 30, 2025 |
Details | Franconia-Springfield Passenger Rail Bypass | Virginia Passenger Rail Authority | $334,223,132 | Fairfax County | 1 | $22,958,821 | Rail | Project Underway | December 31, 2026 |
Details | Route 28 Hot Spot Improvements (Sterling Boulevard to the Dulles Toll Road) | Loudoun County | $12,400,000 | Loudoun County | 3 | $12,400,000 | Roadway | Project Complete | November 30, 2017 |
Details | Liberia Avenue 3rd Lane Eastbound | City of Manassas | $8,851,639 | City of Manassas | 2 | $8,851,639 | Roadway | Not Yet Started | June 30, 2030 |
Details | Northern Virginia ITS/ICM Improvements | Loudoun County | $3,777,000 | Loudoun County | 2 | $2,500,000 | Transportation Technology (e.g. ITS) | Not Yet Started | June 30, 2026 |
Details | Ryan Road Widening (Phase 2) | Loudoun County | $31,500,000 | Loudoun County | 1 | $16,000,000 | Roadway | Not Yet Started | June 30, 2030 |
Details | Route 7 Improvements | Loudoun County | $130,992,500 | Loudoun County | 2 | $20,000,000 | Roadway | Not Yet Started | June 30, 2030 |
Details | North Washington Street Multimodal Improvements Project | City of Falls Church | $22,500,000 | City of Falls Church | 2 | $22,500,000 | Bike and Pedestrian | Not Yet Started | June 30, 2030 |
Details | Herndon Parkway Improvements at Worldgate Drive Extension | Town of Herndon | $6,536,000 | Town of Herndon | 2 | $4,581,000 | Intersection/Interchange | Not Yet Started | June 30, 2030 |
Details | Route 1 at Route 123 Interchange | Prince William County | $68,000,000 | Prince William County | 1 | $3,000,000 | Intersection/Interchange | Not Yet Started | June 30, 2030 |
Details | Connector Buses (8 New) - Fairfax Connector Buses for Tysons to Franconia Service | Fairfax County | $10,000,000 | Fairfax County | 3 | $10,000,000 | Bus | Not Yet Started | June 30, 2027 |
Details | Fairfax County Parkway Widening (Nomes Court to Route 123) | Fairfax County | $115,035,882 | Fairfax County | 1 | $108,000,000 | Roadway | Not Yet Started | June 30, 2030 |
Details | Old Bridge Road Widening: Colby Drive to Minnieville Road | Prince William County | $25,000,000 | Prince William County | 1 | $25,000,000 | Roadway | Not Yet Started | June 30, 2030 |
Details | West End Transitway Phase 1b: South Van Dorn Street and Bridge Design | City of Alexandria | $40,999,440 | City of Alexandria | 1 | $5,000,000 | Bus | Project Underway | June 30, 2030 |
Details | Alexandria Bike and Pedestrian Trails Construction and Reconstruction: Holmes Run Trail | City of Alexandria | $5,500,000 | City of Alexandria | 1 | $5,000,000 | Bike and Pedestrian | Not Yet Started | June 30, 2027 |
Details | Loudoun County Parkway Interchange at US 50 | Loudoun County | $181,152,680 | Loudoun County | 1 | $35,250,000 | Intersection/Interchange | Not Yet Started | June 30, 2030 |
Project Funding Sources
NVTA provides funding for multi-modal transportation improvement projects across Northern Virginia
NVTA Funds Spent
NVTA reimburses funds periodically as the recipient entity spends the funds and submits satisfactory documentation.
Franconia-Springfield Platform Improvements (Project #159)
PROJECT DESCRIPTION
This project includes design and construction to extend the existing north-side (Metro station side) platform at the Franconia-Springfield station by up to 550 feet to allow the north-side platform at the station to be usable by VRE trains on a regular basis. It also includes design and construction of modifications to the south-side platform at the station to allow it to service trains from either side of the platform once a future, third main track is constructed at the station.
Related Project Agreements
Agreement ID | Application Name | Funds |
---|---|---|
2015-159-1 | Franconia-Springfield Platform Improvements | $13,000,000.00 |